1. The selection of copper pipe diameter should strictly follow the selection of pipe diameter for the compressor suction and exhaust valve interface. When the condenser and compressor are separated by more than 3 meters, the pipe diameter should be increased.
2. The suction surface of the condenser should be kept at a distance of at least 400mm from the wall, and the outlet should be kept at a distance of at least 3 meters from obstacles.
3. The inlet and outlet diameters of the storage tank shall be based on the exhaust and outlet diameters indicated on the unit sample.
4. The suction pipeline of the compressor and the return pipeline of the air cooler shall not be smaller than the size indicated in the sample to reduce the internal resistance of the evaporation pipeline.
5. When making the regulating station, each outlet pipe should be sawed into a 45 degree angled mouth and inserted into the bottom end, and the inlet pipe should be inserted into one fourth of the diameter of the regulating station.
6. The exhaust pipe and return pipe should have a certain slope. When the condenser is located higher than the compressor, the exhaust pipe should slope towards the condenser and a liquid ring should be installed at the compressor exhaust port to prevent gas cooling, liquefaction, and reflux after shutdown
At the high-pressure exhaust port, liquid compression occurs when restarting the engine.
7. A U-shaped bend should be installed at the outlet of the air cooler return pipe. The return air pipeline should slope towards the direction of the compressor to ensure smooth oil return.
8. The expansion valve should be installed as close as possible to the air cooler, the solenoid valve should be installed horizontally, the valve body should be vertical, and attention should be paid to the direction of the liquid outlet.
9. If necessary, install a filter on the compressor return line to prevent dirt from entering the compressor and remove moisture from the system.
10. Before tightening all sodium and locking nuts in the refrigeration system, apply refrigeration oil for lubrication to enhance sealing. After tightening, wipe them clean and lock all valve plates tightly.
11. The expansion valve temperature sensing package is fastened with a metal card at the outlet of the evaporator at a distance of 100mm to 200mm, and wrapped tightly with double-layer insulation.
12. After the installation of the refrigeration system, it should be aesthetically pleasing and have consistent colors. There should be no unequal height of pipeline crossings.
13. When welding the refrigeration pipeline, a drainage outlet should be left for nitrogen blowing from high and low pressure for segmented blowing. After the segmented blowing is completed, the entire system should be blown until no dirt is seen, which is considered qualified. Use a blowing pressure of 0.8MP.
14. After the welding of the entire system is completed, an air tightness test should be conducted, and the high-pressure end should be filled with 1.8MP nitrogen. Low pressure end is filled with 1.2MP nitrogen. During the pressurization period, use soapy water for leak detection, carefully inspect all welds, flanges, and valves, and maintain pressure for 24 hours without dropping after basic completion.