Installation of cold storage wall panels

Jul 06, 2024 Leave a message

1. The installation of wall panels should start from the corners. According to the layout diagram, transport the two boards at the corners that need to be installed to the installation site. Drill a hole at the corresponding elevation position in the middle of the board width based on the height of the board beam and the type of angle iron fixing the mushroom head nylon bolt. When drilling, the electric drill should be perpendicular to the board surface, and the mushroom head nylon bolt should be inserted into the hole (sealing paste should be applied inside the nylon bolt body and mushroom head). Tighten the angle iron to make the nylon bolt on the warehouse board surface slightly recessed. When erecting the wall panel, soft materials such as foam shall be padded on the floor trough in contact with the warehouse panel to prevent damage to the warehouse panel. After the two corner wall panels are neutral from the floor trough, the plane position of the wall panel and the perpendicularity of the warehouse panel shall be adjusted in time according to the setting out position, and the top elevation of the wall panel shall be checked to see if it is correct (it shall be checked from beginning to end). After the position of the wall panel is correct, weld the angle iron pieces onto the beam and fix the inner and outer corners (apply a sealing paste at the contact point between the inner sides of the corner board and the warehouse board). When welding angle iron parts, the corner iron parts of the storage plate should be covered with a shield to prevent the high temperature of welding during arc welding from damaging the storage plate and splashing welding slag onto the storage plate.
2. After installing the two wall panels at the corner, start installing the next wall panel along the direction of the corner. Before installing the next wall panel, two layers of white sealant should be applied to the convex groove or groove of the storage board on the ground (the sealant should be applied at the corner of the convex groove or groove of the storage board). The sealant applied to the convex groove or groove should have a certain height and should be dense, continuous, and uniform. The installation method is the same as that of the first wall panel.
3. First, use a hammer to strike the square wood that is placed on the polyurethane storage board between the two storage boards, so that the boards are tightly attached to each other. Two sets of connecting pieces are wedged tightly between the wall panels, and the two sets of connecting pieces are fixed on the upper outer and lower inner sides of the gap between the wall panels. The connecting pieces on the lower inner side should be as close as possible to the bottom so that the post poured concrete can cover the connecting pieces. The gap between boards should be kept at around 3mm wide after being wedged tightly with connectors. If it does not meet the requirements, the board should be removed, the board edges should be trimmed, and then reinstalled to make the board gap meet the requirements. When fixing the connectors, it is important to secure the two components of a set of connectors separately at the edges of the convex and concave storage plates, using rivets with a diameter of 5X13. The distance between the connectors should be sufficient to tighten the two storage plates. When wedging the wedge iron, the hammer should be kept perpendicular to the wedge iron to avoid damaging the storage plate. The wedge iron in the upper and lower parts should be wedged together and fixed with rivets.